Three men do as much work as 4 boys do and the 4 boys can together complete work in 21 days. In how many days will 9 men and 2 boys complete the same work?
Five men and 2 boys can do as much work in 30 days as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
Sachin alone can complete a piece of work for Rs. 8,500 in \(8\frac{1}{2}\) days. But with the help of Vishnu, the work is completed in 6 days. The share to be paid to Vishnu is:
8 children and 12 men complete a certain piece of work in 9 days. If each child takes twice the time taken by a man to finish the work, in how many days will 12 men finish the same work ?